Does the Philippines have the compute for its AI plans? 50 MW today, 1.5 GW promised

Every known data center in the Philippines with its capacity in MW, its operators and the investors behind it, and the distance between what is energized and what is announced. 65 public sources, read once and linked into one graph.

73–200 MW
operating, depending on who counts
~50 MW
built for AI workloads, one site
2–3 GW
announced to 2030, mostly unbuilt
10,000
Blackwell Ultra GPUs announced for Q1 2027, the first large cluster

Summary

The Philippines has a national AI strategy, a state AI platform under construction and about two dozen operating data centers. Nearly all are colocation halls of 1 to 30 MW built for banks, telecoms and outsourcers. One site, about 50 MW, was designed for AI workloads. In September 2026 the government set a target of 400 MW by 2030 and 1.5 GW by 2033.

Operators built ahead of demand and keep building: Globe says it will spend at least $1 billion on AI and data centers in 2027, Converge is planning an 80 MW site for AI, and the first large GPU cluster, more than 10,000 Blackwell Ultra chips, is scheduled for the first quarter of 2027. No hyperscaler has committed to a Region. The largest number in the pipeline, 250 MW in Laguna, is a letter of intent from a Gulf conglomerate, and the first data center REIT was deferred to 2027 after three rate rises. Public money goes to connectivity and training, not compute.

Built against targetmegawatts; 2026 bar shows the range of operating estimates
0 500 1,000 1,500 50–200 MW2026, built 400 MW2030, target 1,500 MW2033, target AI-ready, about 50 MW all operating, up to 200 MW government target
On the generous 200 MW count, the fleet has to grow seven times in seven years. On the AI-ready count it has to grow thirty times.

What the study asks

01Map the physical layer. Every facility with operator, location, disclosed capacity, status and source.
02Classify the capital. Who finances each project, grouped by origin and by what the money wants.
03Measure the gap. Operating against announced, and why seven sources give seven capacity figures.
04Read the agenda. Which organizations dominate the public record, on which topics, in which places.
05Set the markers. Six events in 2027 that would change the map.

How it was built

The study is a knowledge graph. Each public source is read once, coded into the same set of fields, and linked to the organizations, places, facilities and deals it mentions. Every chart on this page is a query against that graph, and every number traces back to a source document.

The corpus

65 documents from September 2022 to April 2026: Philippine national press, industry press, operator releases, government documents and two analyst reports. A source enters when it states a fact about a facility, a deal or a policy. Private briefings are excluded.

Sources by type65 documents
National news, Philippines35 Industry press10 Press releases5 International news4 Regional outlets3 Analyst reports2 Commentary2 Vendor marketing2 Government1 Think tank1
Documents per periodthe February 2026 spike
2 2022 3 2024 5 Q1 25 6 Q2 25 5 Q3 25 10 Q4 25 10 Jan 26 15 Feb 26 7 Mar 26 2 Apr 26
The KKR–Singtel deal for STT GDC, the DAMAC and Masdar announcements, the Bifrost cable going live and the NAICRI launch fell within eight weeks of each other.

Coding

Every document gets the same fields: source type, date, geography, primary topic, organizations and facilities mentioned, investment events (investor, target, amount, instrument, origin of capital, stage), relations, key facts, consistency flags, and the sources the document itself cites. A press release and a newspaper investigation are coded the same way, so they can be compared.

Each facility reads as one sentence: [operator] runs or plans [MW] at [location], financed by [capital tier], built for [tenant type], currently [status], per [n sources], with [conflicts] where sources disagree.

When two sources disagree, both values stay and the disagreement gets an identifier. The study reports ranges, because the spread usually says something: operators and surveyors count different things.

The graph

433 entities, about 570 links, 28 named patterns such as the capital tiers in section 2 and the hyperscaler bypass in section 3. The figure shows the organizations and facilities that appear together in at least two documents; node size is the number of documents, line weight is how often two entities share one.

Who appears with whom34 entities, co-mentions in two or more documents
DICT PLDT VITRO Globe Telecom STT GDC Meta VITRO Sta. Rosa AWS IBPAP DTI Google Digital Halo BIEN Digital Edge STT Fairview Meralco Microsoft DOST DCPH Converge ICT Amazon Trece Martires Concentrix MNL1 World Bank DOLE TESDA DepEd CHED YCO Cloud InfiniVAN Bifrost PEZA operators facilities and cables government hyperscalers industry and labor
Three clusters. Operators and their facilities on one side, government agencies on the other, hyperscalers in between. Meta sits closer to labor and cable stories than to any data center.
What the graph holdsnodes by type
Organizations161 People107 Articles65 Places40 Concepts28 Data centers and cables32
Organizations by role161 organizations, several roles possible
Government agencies15 Developers and REITs12 Colocation and DC operators10 Telecoms9 BPO providers8 Submarine cable7 Private equity7 Hyperscalers7 Academic7 Think tanks and civil society8 Industry associations6 Enterprise customers5
Fifteen government agencies to ten operators: in the public record, agencies outnumber builders.

1. What is built

Twenty-two facilities can be documented: twenty-one in the corpus and one announced in October 2026, plus two cable landing stations and a handful of public compute sites. Sixteen operate. Capacity is disclosed for about half. Independent counts of the whole market range from 28 to 44 facilities depending on what counts as one.

Facilities by status22 facilities
22 Operational16 (73%) Announced or planned4 (18%) Proposed2 (9%)
The six unbuilt projects carry 466 MW of announced capacity, more than the sixteen operating sites combined on any count.
Largest projects by disclosed capacitymegawatts, full build-out for campuses
DAMAC Laguna (proposed)250 MW STT Fairview campus, 4 buildings124 MW VITRO Cavite (planned)100 MW Converge Luzon AI site (planned)80 MW VITRO Sta. Rosa50 MW A-FLOW Laguna 1 (announced)36 MW YCO Cloud Malvar, energized30 MW HIVE Hybrid DC22 MW Converge Angeles12 MW Digital Halo MNL112 MW NARRA1, Digital Edge10 MW operating or in phased operation announced, planned, proposed
STT Fairview is the full four-building plan; the operator expects 30 to 35 MW by the end of 2026. VITRO's Cavite site is reported as both Trece Martires (2025) and General Trias (October 2026). YCO Cloud Malvar is a single secondary figure.

The market total depends on who counts and what. Surveys of energized, lettable IT load give 73 to 100 MW. A telco chief executive cited 140 MW live in September 2026. The government says above 180. Adding operator claims, which include shell capacity and committed power, gives about 200. One press figure of 632 MW has no published method. All seven stay in the record. The spread is itself a finding: the country has no agreed way to count its own capacity.

Seven answers to one questionoperating capacity, megawatts, conflict record 005
datacenterHawk, Nov 202573 MW Cushman & Wakefield, Manila, H1 202690 MW DCAP, Sep 2026100 MW Globe, Bloomberg interview, Sep 2026140 MW Government figure, Sep 2026180 MW Operator-claim aggregation200 MW Highest press figure, 2025632 MW independent surveys industry and government statements unexplained
Documented data center facilities in the Philippines
FacilityOperatorLocationStatusMWCapital behind itSource
DAMAC Digital LagunaDAMAC DigitalLagunaproposed250Gulf corporate41
STT GDC Fairview (campus, 4 buildings)STT GDC PhilippinesQuezon Cityoperational, phased124Foreign PE3, 7
VITRO Cavite (General Trias or Trece Martires)VITRO / PLDTCaviteplanned100Domestic telco15, 71
Converge Luzon AI siteConverge ICTCavite, Laguna or Batangasplanned80Domestic telco73
VITRO Sta. RosaVITRO / PLDTLagunaoperational~50Domestic telco12
YCO Cloud MalvarYCO CloudBatangasoperational, GPU cluster Q1 202730Domestic, Singapore partner69
A-FLOW Laguna 1A-FLOWLagunaannounced36Foreign PE18
HIVE Hybrid Data CenterBeeinfotech PHMetro Manilaoperational22Domestic30
Converge AngelesConverge ICTPampangaoperational12Domestic telco27
Digital Halo MNL1Digital HaloRizaloperational12Foreign PE, bank project finance21
NARRA1Digital EdgeLagunaoperational10Foreign PE22
Converge CaloocanConverge ICTMetro Manilaoperational3Domestic telco27
Equinix MN1, MN2, MN3EquinixMetro Manila, Caviteoperational—Foreign listed operator33
DITO Super CoreDITO TelecommunityBatangasoperational—PH–Chinese state-linked36
AWS Local Zone ManilaAWSMetro Manilaoperational—Hyperscaler, direct44
STT Cavite 2STT GDC PhilippinesCaviteannounced, testing and commissioning—Foreign PEPH-2026-0007
Converge PasigConverge ICTMetro Manilaoperational—Domestic telcoPH-2026-0017
VITRO MakatiVITRO / PLDTMetro Manilaoperational—Domestic telcoPH-2024-0002
VITRO ParañaqueVITRO / PLDTMetro Manilaoperational—Domestic telcoPH-2024-0002
VITRO PasigVITRO / PLDTMetro Manilaoperational—Domestic telcoPH-2024-0002
Bataan Nuclear Power Plant conversion—Bataanproposed, feasibility study600—PH-2026-0002, PH-2026-0003
21 of 22 facilities listed; 1 row is still being added from the full set. Download the CSV.

2. Whose money

The corpus records 29 investment events. Grouped by origin and by what the money wants, they fall into eight tiers that behave differently. Private equity wants hyperscale tenants and an exit in five to ten years. Domestic telcos build for their own enterprise base. Gulf capital arrives on sovereign timeframes and pairs data centers with power.

Deals on a timeline9 events that shaped the market
Oct 2022 EdgeConneX and FLOW joint ventures announced Apr 2025 VITRO Sta. Rosa, $350M Oct 2025 World Bank loan to DICT Jan 2026 DAMAC $3B, Masdar $15B Feb 2026 KKR and Singtel take STT GDC Jul 2026 AWS proposes $5B Sep 2026 DICT masterplan, 1.5 GW Sep 2026 YCO Cloud and Aolani: 10,000 GPUs for Q1 2027 Oct 2026 Converge plans 80 MW AI site; VITRO REIT IPO deferred
Colors follow the tiers below: blue for private equity and listed operators, orange for domestic telcos, teal for Gulf and hyperscaler capital, grey for public money.
Announced amounts by dealUS$ million where disclosed; platform commitments are not Philippines-only
Masdar, renewable platform (AE)$15B DAMAC Digital, DC platform (AE)$3B STT GDC Fairview campus$1B Partners Group, Digital Halo$400M DITO Batangas campus$362M VITRO Sta. Rosa$350M World Bank loan to DICT$287M Equinix, TIM assets (US)$180M Beeinfotech HIVE$150M Converge, Bifrost IRU$100M RCBC project finance, MNL1$47M InfiniVAN, Aurora CLS (JP)$31M Gulf capital foreign PE and listed operators domestic public and multilateral
Masdar's $15B is a renewable platform that includes power for data centers; DAMAC's $3B covers an Asian platform of which Laguna is one site. Both are commitments, not spending.

The largest numbers come from entrants who have not poured concrete. The public contribution to AI compute, the NAICRI platform at about $46 million, is one hundred to one thousand times smaller than the private foreign commitments. Public money goes to connectivity (the World Bank loan to DICT) and training, not to compute.

Investment events by origin of capital29 events
Philippines9 UAE3 United States3 Singapore3 Japan1 Indonesia1 United Kingdom1 Multilateral1 Not disclosed7
Domestic events are the most numerous and the smallest. The three UAE events carry the largest sums.

The eight tiers

1aForeign private equity, LP funds
Stonepeak, KKR, EQT, PAG
Hyperscale-target capacity, exit in 5 to 10 years
1bForeign PE, insurance capital
Arch Capital
Long-dated yield
2Manila conglomerates with regional reach
Ayala Land, Aboitiz
Land and power banks, JV partner to tier 1
3aDomestic telco, hyperscale ambition
VITRO / PLDT
Build first, attract a hyperscaler later
3bDomestic telco, sovereignty positioning
Converge, Cebuana Lhuillier
Government and data-residency demand; no megawatt race
4Philippine–Chinese state-linked
DITO Telecommunity
Third telco, China Telecom anchor
5Multilateral
World Bank
Connectivity and public platforms
6Hyperscaler, direct
AWS Local Zone
Edge presence; Region still a proposal
7Gulf corporate balance sheet
DAMAC Digital
Family conglomerate horizon, 250 MW intent
8Gulf sovereign, state-owned
Masdar
Renewables paired with DC load

Capital that prefers Singapore, Malaysia and Indonesia (tier 1, and the BlackRock–GIP–MGX consortium) treats the Philippines as adjacent. Capital arriving now (tiers 7 and 8) treats the power constraint as the opportunity.

3. The hyperscaler question

Every major cloud serves Philippine customers from Singapore. AWS runs a Local Zone in Manila for latency-sensitive workloads; Azure and Google Cloud have no Philippine presence. In July 2026 AWS proposed up to $5 billion over 15 years, including a possible Region. It remains a proposal. Two unnamed US hyperscalers were doing due diligence on Luzon sites of about 200 MW each in September 2026; the DICT secretary who said so resigned a month later.

Hyperscaler presence in the Philippines
HyperscalerPhilippine presenceServes the country fromStatus
AWSLocal Zone, ManilaSingapore RegionRegion proposed, July 2026
Microsoft AzurenoneSingapore Regionno announcement
Google CloudnoneSingapore Regionno announcement
Alibaba Cloudlimitedmulti-region SEA—
Tencent Cloudlimitedmulti-region SEA—
Metano confirmed facilitySingapore and globalBifrost cable investor

STT GDC's Fairview campus and VITRO's planned Cavite site are both designed for a hyperscale tenant that has not been named. Capacity built ahead of the anchor customer, on the bet that a Region follows, is the hyperscaler bypass pattern. The bet paid in Malaysia and Indonesia; in the Philippines it is still open.

The Bifrost cable landed in Davao and went live in February 2026. Read from Singapore, the Philippines is a transit market on the way to the hub. Read from Manila, it is a landing point for the region. Which reading wins is the same question as whether a Region gets built.

4. Who sets the agenda

DICT is mentioned in more documents than any operator. Labor is the fourth largest topic, which is unusual for a data center market and is the subject of a separate study.

Most-mentioned organizationsdocuments mentioning each, of 65
DICT14 PLDT13 VITRO12 Globe Telecom10 STT GDC Philippines9 Meta9 AWS8 IBPAP6 DTI6 Google6 Digital Halo5 Digital Edge4 Meralco4 Microsoft4 Converge ICT4
Meta appears as often as STT GDC without owning a Philippine facility: the Bifrost cable and the content-moderation workforce keep it in the story.
What the documents are aboutprimary topic per document
Infrastructure17 Regulation and policy14 Market overview8 Labor7 Investment6 Technology3 Renewable energy2 M&A2 Market analysis2 Other3

5. Where

Metro Manila dominates the record. Laguna is second, ahead of any single Manila district, because the three largest AI-oriented projects (VITRO Sta. Rosa, DAMAC, NARRA1) sit there. Davao appears because of the cable.

Places mentioneddocuments, places can overlap
Metro Manila27 Laguna13 Makati7 Sta. Rosa City6 Cavite6 Batangas4 Davao Region4 Davao City3 Rizal3 Calabarzon2 Pasig2
A site map sized by megawatts is the next addition; coordinates for all 21 facilities are in the graph.

6. Power

The grid generated about 62 percent of its electricity from coal in 2023, the highest share in the region. A fleet growing from tens to hundreds of megawatts adds concentrated load unless each site brings generation. Two responses appear in the record: dedicated switching stations built with Meralco for Fairview and Sta. Rosa, and the Masdar–DAMAC pairing, a renewable platform and a data center platform announced by the same government in the same week. If the pairing holds, the power constraint becomes a reason for Gulf capital to enter. If it does not, the 1.5 GW target has no grid to plug into.

Since the corpus closed

Developments between the end of the coded corpus and publication, checked against primary sources on November 3, 2026.

Developments since the corpus closed
DateWhat happenedSource
Sep 8DICT says two unnamed US hyperscalers are doing due diligence on Luzon sites, each weighing an initial 200 MW built over five years; corridors examined so far are Bataan–Clark and Batangas–Aurora.BusinessMirror; Tech Pilipinas
Sep 21Physical Intelligence (US) registers with PEZA to build a data factory for robot-motion data, the first of its kind in the country. No capacity or investment figure.BusinessWorld; Context.ph
Sep 28YCO Cloud and Aolani (Singapore) announce more than 10,000 NVIDIA Blackwell Ultra GPUs in GB300 racks, first phase in Q1 2027, on dedicated renewable power; site and megawatts undisclosed. Part of Aolani's 22,000-GPU, 100 MW plan for Malaysia and the Philippines.TechNode Global; Newsbytes
Sep 29Globe says it will spend at least $1 billion in 2027 on AI and data centers and may list the data center venture. STT GDC Philippines: five facilities, 30 to 35 MW by end-2026, 124 MW over three years. Market context cited: 44 data centers, 140 MW live, 43 MW under construction, 221 MW planned.Light Reading; W.Media
Sep 30Meralco PowerGen and VITRO REIT sign a memorandum to study data centers co-located with renewable generation. No sites or megawatts.Context.ph; Philstar
Oct 6PLDT defers the VITRO REIT IPO to 2027, citing market conditions and three rate rises; the portfolio was eight sites totaling about 24 MW. The 100 MW Cavite site is restated as planned, now placed in General Trias.PLDT 6-K; Philstar; W.Media
Oct 10–19The DICT secretary who sponsored the masterplan resigns; the head of the Social Security System is appointed and takes over October 19 with Internet prices and ISP licensing as stated priorities. No statement on the masterplan.Manila Times; Philstar; Newsbytes
Oct 13The President, in Singapore, ties nuclear power to data centers and AI. The Palace says the Pax Silica framework for the 1,620-hectare New Clark City park will be signed before the end of 2026; BCDA projects $40 to 70 billion of investment. The BCDA said in August the site is for manufacturing, not data centers.Philstar; PNA via SunStar
Oct 20–21Converge plans two new Luzon data centers in Cavite, Laguna or Batangas, one of 80 MW, its largest, for AI; capex reported as at least ₱5 billion by one outlet and about $800 million by another. Angeles site: 12 MW, expandable to 36.Philstar; W.Media; Inquirer
Oct 27A commercial market report counts 32 existing and 10 upcoming data centers and a pipeline above 700 MW; ePLDT above 60 MW of IT capacity and a 30 percent share. Methodology not published.GlobeNewswire

Findings

01The fleet is small and traditional, and the first GPU cluster is a year away. Sixteen operating facilities, nearly all colocation halls of 1 to 30 MW. One site of about 50 MW was built for AI. Independent counts put the market at 73 to 100 MW energized; operator claims reach 200. The first cluster of more than 10,000 GPUs is scheduled for the first quarter of 2027.
02The pipeline is large and unbuilt. Two to three gigawatts announced through 2030. The largest project, 250 MW in Laguna, is a letter of intent. Three of the five largest numbers on the capacity chart have no concrete under them.
03Public money is not going into compute. The state AI platform is funded at about $46 million. The World Bank loan funds connectivity. Private foreign commitments are 100 to 1,000 times larger.
04No hyperscaler has committed, and the official who was courting them has left. AWS has proposed a Region; two unnamed US hyperscalers were evaluating 200 MW sites in September. Azure and Google serve the country from Singapore. The DICT secretary resigned in October; the successor has not spoken on the masterplan.
05The arriving capital has a different thesis. Private equity prefers Singapore, Malaysia and Indonesia. Gulf corporate and sovereign capital enters the Philippines with power attached and treats the grid constraint as the opening.
06The state speaks louder than the builders. Fifteen government agencies against ten operators in the graph; DICT is the most-mentioned organization in the corpus.
The Philippines does not yet have the compute for its AI plans. It has the sites, the operators and, since 2026, foreign capital interested in building. Whether 1.5 GW arrives depends on one hyperscaler signing and on Masdar and DAMAC turning commitments into sites.

Questions this page answers

How many data centers are in the Philippines?

Twenty-two documented facilities, sixteen of them operating, as of November 2026. Independent counts range from 28 to 44 depending on whether every hall, campus and edge site counts as one.

How much data center capacity does the Philippines have?

Between 73 and 200 MW operating, depending on the counting method. Independent surveys give 73 to 100 MW of energized IT load; operator claims add up to about 200. Roughly 50 MW is built for AI workloads.

Does AWS have a Region in the Philippines?

No. AWS runs a Local Zone in Manila for latency-sensitive workloads and serves the country from its Singapore Region. In July 2026 it proposed up to $5 billion over 15 years, including a possible Region. Azure and Google Cloud have no Philippine presence.

Who are the largest data center operators in the Philippines?

By operating capacity: VITRO (PLDT), STT GDC Philippines, Converge ICT, Equinix, Beeinfotech, Digital Edge and Digital Halo. By announced capacity the largest project is DAMAC Digital's proposed 250 MW campus in Laguna.

What is the Philippine government's data center target?

The DICT AI+ Infrastructure Masterplan of September 2026 targets 400 MW by 2030 and 1.5 GW by 2033, with $34.4 billion of total investment of which $13.5 billion is public.

What to watch in 2027

AWS Region decisionA signed agreement, a land purchase or a named site moves the country from bypass to anchor. Silence through 2027 confirms the Singapore-hub reading.
STT Fairview buildings 2 to 4124 MW on paper, about 1 MW of customer load in practice. Energization of the second hall is the first hard test of the pipeline.
VITRO Cavite100 MW planned for an unnamed tenant. Construction without a tenant extends the bypass bet; a tenant announcement ends it.
First DAMAC and Masdar megawattsA site, a permit or a power purchase agreement would convert the largest numbers in the market from commitments to projects.
YCO Cloud and Aolani, first quarter 2027More than 10,000 Blackwell Ultra GPUs are promised for Malvar. Delivery would be the first large AI cluster in the country; slippage would say what the financing looks like.
The new DICT secretaryThe masterplan sponsor resigned in October. Whether the 400 MW and 1.5 GW targets survive the handover is not yet known.

The weekly monitor tracks these six. When one moves, the table changes and the changelog records it. Dates for the region's conferences are on the events calendar.

Sources and citation

Selected sources
  1. DICT, AI+ Infrastructure Masterplan, September 2026
  2. Newsbytes Philippines, AWS proposal, July 8, 2026
  3. STT GDC Philippines, Fairview campus materials, 2025–2026
  4. Cushman & Wakefield, Asia Pacific data center update, February 2026
  5. datacenterHawk, Philippines market note, November 2025
  6. DataCenterDynamics, KKR and Singtel acquisition of STT GDC, February 2026
  7. Inquirer Global Nation, DAMAC Digital, January 2026
  8. Eco-Business, Masdar framework agreement, January 2026
  9. Developing Telecoms, Converge IRU on Bifrost, August 2025
  10. DOST and OpenGov Asia, NAICRI, May 2025
  11. Light Reading and W.Media, Globe chief executive interview, September 29 to October 1, 2026
  12. TechNode Global and Newsbytes, YCO Cloud and Aolani release, September 28 to 29, 2026
  13. PLDT, PSE disclosure on VITRO REIT, October 6, 2026
  14. Philstar and W.Media, Converge new Luzon sites, October 20 to 21, 2026
  15. Manila Times and Philstar, DICT leadership change, October 10 to 14, 2026
All 65 in the full list, with the fields each was coded into.
Cite this study
Gaintdinov, R. (2026). Does the Philippines have the compute for its AI plans? Philippine Data Center Map 2026. gaintdinov.com/research/philippines-data-center-market. Accessed [date].
Changelog
November 2026 first public version: 22 facilities, 29 investment events, 65 sources.
Method notes
A facility enters the table when an operator, regulator or landowner names it publicly. Capacity is the operator's disclosed figure; conflicting values are both kept and logged. Capital tier follows section 2. Mention counts are per document. The corpus is re-read monthly.